Domain Interchange

Written by Dene Macleod

cr domainint 001

Location: Melbourne, Victoria

Client: Yarra Trams

Role of Coleman Rail: Head Contractor

Project Summary: Construct Only; Brownfield Redevelopments; Light Rail

Project Scope

A $10m redevelopment of Melbourne's largest tram interchange, the project was completed in a 10 day occupation. Tram operations servicing about 25,000 passengers per day were maintained throughout the works using 4 no. temporary tram stops with turn-back facilities using temporary crossovers. The works included 2 no. 66m long double-sided DDA compliant platforms; 10 no. turnouts, seven being automated; and the complete reconstruction of the intersection and traffic signalling system.

Coleman Rail Contact Person: Chris Morralee